Customer Success Stories > Several Brief Case Studies

Design & Fabrication Case Study
An Automobile Paint Plant

Modules Used: CADPIPE Commercial

Results:
-0% Material Waste on project.
-130 fabrication drawings done.
-Contractor awarded bonus for finishing ahead of schedule.
-Fabrication done in Ohio, Installation done with local labor.

Manpower: 2 CADPIPE Operators.

Time frame: 3 Months.
Industrial Case Study
$7 Million Refinery Document Upgrade Project employing Aerial Photogrammetry

Modules Used: CADPIPE P&ID, CADPIPE 3D Design

Results:
-1,004 P&ID Drawings.
-1,500 Pipelines in 10 3D models.

Manpower: 4 CADPIPE Operators.

Time frame: 6 Months.
Industrial Case Study
$150 Million Recycling Facility Project

Modules Used: CADPIPE ORTHO, CADPIPE ISO

Results:
-80 Plan, Elevation, and Detail Drawings.
-1,360 Automatic Isometric Spools.

Manpower: 3 CADPIPE Operators.

Time frame: 3 1/2 Months.
Commercial Pipe Case Study
$30 Million East Side Reservoir Project

Modules Used: CADPIPE Commercial

Results:
-3D Model Created
-160 Plan, Elevation, and Detail Drawings.
-30 Automatic Isometric Spools.

Manpower: 3 CADPIPE Operators.

Time frame: 3 1/2 Months